Metlox Plaza Tree Replacement to Begin
Sep 16, 2024 09:14AM ● By Mb News Staff

• Wednesday, September 18, from 7:00 a.m. to 4:00 p.m.: Remove and store all tables and chairs and put up a temporary fence to enclose the construction area. Also, remove all nine trees and grind tree stumps.
• Thursday, September 19, from 7:00 a.m. to 4:00 p.m.: Finish grinding tree stumps and start hand-digging the nine planters. Start installing olive trees and tree grates.
• Friday, September 20, from 7:00 a.m. to 4:00 p.m.: Finish installing the remaining olive trees and tree grates. Power wash the area, remove the temporary fence, and replace the tables and chairs.
Businesses will remain open and access to the businesses will be unobstructed during the operation.
Also worth noting: Painting of the three stairwells began last week, and the work is anticipated to be finished by the end of the month.